Long Beach ADU Rules 2026: State Law, Pre-Approved Plans and SB 9

Long Beach has no local ADU ordinance right now, so every ADU is reviewed under state law. Here is what a Long Beach lot can hold, how the permit counter works, and what changes on January 1, 2027.

By Kasra ErfanianPublished ← All guides

Illustration of a Long Beach bungalow with a detached backyard ADU

Informational only, not legal advice. ADU rules change often and differ by city. Confirm with your local planning department before you rely on anything here.

Long Beach is one of the few large California cities with no local ADU ordinance on the books. The city's ADU page says Long Beach Municipal Code section 21.51.276 "no longer applies" and that it is administering State ADU Law directly until a new local ordinance is adopted. In practice, the city's Planning Information Bulletin IB-PZ-001 is the rulebook. This guide to Long Beach ADU rules walks through what that bulletin allows as of November 18, 2026, how the permit counter works, and what changes on January 1, 2027 when AB 956 takes effect.

What this means for your lot

Because Long Beach applies state law with no local layer on top, you get the state minimums and nothing stricter: no lot coverage, floor-area or open-space limits on ADUs, 4-foot side and rear setbacks, and no parking in most of the city. Check the bulletin's current date before you design; it changes as state law changes, and this is not legal advice for your specific lot.

Why Long Beach reviews ADUs under state law only

The bulletin says the city "does not currently have an adopted local ADU ordinance," so all ADU and JADU projects "are reviewed strictly in accordance with State ADU law." It stops applying once the council adopts one; we found none as of today.

For builders that is mostly good news: with no ordinance, the city cannot add objective standards on top of the state floor. The city says Long Beach "ranks as the highest per-capita producer of ADUs in California." When an ordinance arrives it may add design rules, so a permit filed under today's bulletin has value.

How many ADUs can I build in Long Beach?

Single-family lots

Under Table 1 of IB-PZ-001, a single-family lot can have one conversion ADU, one new detached ADU and one JADU. Our two-ADU rule guide explains how those state categories stack.

Unit typeHow manyMaximum size
Conversion of part of the house1 ADUNo limit
Conversion of a garage or accessory building(same ADU)No limit; only a 150 sq ft addition for access, such as a stair
Attached addition to the house(same ADU)50% of the house or 800 sq ft, whichever is more
New detached ADU1 ADU800 sq ft
JADU (inside the house or attached garage)1 JADU500 sq ft

Every unit must be at least 150 square feet, and ADU size is measured to the interior walls.

Multifamily lots

On a lot with an existing apartment building, the city allows detached ADUs up to eight or the number of existing permitted units, whichever is less. That is SB 1211 at work; see our SB 1211 guide. Attached non-habitable space can also be converted: one ADU or 25% of the existing units, whichever is more. No JADU is allowed on a multifamily lot.

Long Beach ADU height, setbacks and parking

Height

  • New detached ADU: 16 feet, or 18 feet within a half-mile walk of major transit or a high-quality transit corridor (plus up to 2 feet to match a sloped roof on the house), or 18 feet on a lot with an existing multi-story apartment building.
  • Attached ADU or addition: 25 feet or two stories, or the zone's height limit if lower.
  • Conversions: keep the existing building height.

The city's "SB 9 Parking Exemption and ADU Height Exception Map" shows which lots get 18 feet.

Setbacks

New construction needs 4 feet on the side (or less if the zone allows) and 4 feet at the rear, measured to the centerline of an alley where there is one. That is real square footage on alley lots. Front setbacks follow the zone, but an ADU may encroach into the front yard if there is no other way to fit an 800-square-foot unit. Conversions of permitted buildings keep their existing setbacks.

Parking

No parking is required within a half-mile walk of any transit stop, in a historic district, for conversions and JADUs, near car share, or inside the city's Parking Exempt Area.

Long Beach pre-approved ADU plans and the permit process

The city's Pre-Approved ADU Program (PAADU) currently lists two designs: PAADU-01 "The Sevila," an 800-square-foot, two-bedroom, two-bath unit, and PAADU-02 "The Casita," a 415-square-foot one-bedroom. The city says they can be approved over the counter, with a permit issued "the same day." They are for new construction only. For how state law treats pre-approved plans, see our AB 1332 guide.

Custom plans are filed in person at the Permit Center, as a PDF on a USB drive, with plan check fees paid that day; the city does not take online submissions. Historic and Coastal Zone projects cannot go over the counter and need a Certificate of Appropriateness or an administrative coastal permit, both without a hearing.

What changes in 2027, and how SB 9 fits

AB 956 was chaptered September 29, 2026 and takes effect January 1, 2027. It lets a single-family lot have two new detached ADUs instead of one; if you build both, the city no longer has to approve a JADU. Details are in our AB 956 guide. Because Long Beach applies state law directly, there is no local ordinance to amend first; confirm the updated bulletin with Planning before you file. ADU impact fees also change; see our SB 1117 guide.

For a second full house, Long Beach allows SB 9 units on R-1 lots with no more than one existing house; they pay the same fees as any new home, and no lot split is required. See our SB 9 guide.

Our recommendation: on a standard Long Beach single-family lot, design the backyard for two detached units now, file the first under today's rules, and add the second after January 1, 2027. Price both against our ADU cost guide (typical ranges; your bids will differ), and run the address in Parcy to see the pathways side by side.

Frequently asked questions

Does Long Beach have an ADU ordinance?

Not right now. The city says Long Beach Municipal Code 21.51.276 no longer applies and it reviews every ADU and JADU directly under State ADU Law until a new local ordinance is adopted.

How many ADUs can I build in Long Beach?

On a single-family lot today: one conversion ADU, one new detached ADU up to 800 square feet, and one JADU. With an existing apartment building: up to eight detached ADUs, capped at the number of existing units.

How tall can an ADU be in Long Beach?

A new detached ADU is limited to 16 feet, or 18 feet within a half-mile walk of major transit or a high-quality transit corridor, plus up to 2 feet to match a sloped roof on the main house. An attached ADU can reach 25 feet or two stories, or the zone height limit if lower.

Does Long Beach have pre-approved ADU plans?

Yes. The Pre-Approved ADU Program has a 415-square-foot one-bedroom and an 800-square-foot two-bedroom, for new construction only, approvable over the counter.

Do I need parking for an ADU in Long Beach?

Usually not. No parking is required within a half-mile walk of transit, in a historic district, for conversions and JADUs, or inside the city's Parking Exempt Area.

Official bill text

Sources

  • Long Beach ADU rules
  • Long Beach ADU ordinance
  • Long Beach pre-approved ADU plans
  • how many ADUs can I build in Long Beach
  • Long Beach ADU setbacks and height
  • Long Beach ADU parking
  • Long Beach SB 9
  • Long Beach multifamily ADU
  • Long Beach

Stay ahead of the next ADU bill.

New California housing bills, what they mean for your lot, and news from Parcy and Kaz Capital Group. A few emails a month.

By subscribing you agree to receive email from Parcy and Kaz Capital Group — bill updates, guides, and other news from us. Unsubscribe anytime. Privacy.

Informational only. Not legal, architectural, or investment advice. Confirm current rules with your local planning department.