Cost & finance

SB 1014: Cities Must Estimate Required Site Improvements in 2027

Signed September 29, 2026, SB 1014 gives builders an early list of the sidewalks, utility upgrades and street work a city expects, and locks the list at building permit, starting January 1, 2027.

By Kasra ErfanianPublished ← All guides

Illustration of a California residential lot with new curb, sidewalk and utility lines marked along the street frontage.

Informational only, not legal advice. ADU rules change often and differ by city. Confirm with your local planning department before you rely on anything here.

SB 1014, by Senator Tim Grayson, was signed by Governor Newsom on September 29, 2026 and chaptered as Chapter 806, Statutes of 2026. It goes after one of the least predictable costs in a housing project: the onsite and offsite improvements a city attaches to your permit. Starting January 1, 2027, you can ask the city for a written list and estimate of those improvements up front, and once your building permit application is complete, the city has to put every required improvement on one itemized list and generally live with it.

What this means for your lot

If you're planning a small-lot subdivision, a multi-unit project or any housing development, check the SB 1014 box in 2027: request the preliminary estimate of required improvements in your preliminary application. You get the city's list within 30 business days, before you've spent on full plans. Then, at the building permit stage, the city's itemized list becomes the ceiling, with narrow exceptions. Budget a contingency anyway; the early estimate is not binding, and your city's engineering standards still decide what the work costs.

What SB 1014 changes: two lists, two deadlines

The bill adds Government Code section 65941.3 to the Permit Streamlining Act and creates two separate obligations.

Preliminary estimatePostentitlement itemized list
WhenYou request it with your preliminary application (or full application if you skip the preliminary)Automatic, after the city deems a postentitlement permit application complete
Deadline30 business days from your request30 business days from completeness
ContentsGood-faith list of the types of onsite and offsite improvements that may be required; cost estimate for any the city builds itselfItemized list of all onsite and offsite improvements required for that permit
Binding?No, informational onlyYes: the city generally can't require improvements left off the list

"Improvement" is defined broadly: streets, parks, public transit, utilities, water, wastewater, flood protection, fire and police facilities and similar infrastructure. Special districts count as public agencies; school districts do not.

Offsite improvements cost: why an early estimate matters

On the small infill projects we build, offsite work is where budgets break. Frontage work often isn't known until a public works plan checker reads your civil set months later. A new curb, gutter and sidewalk across a 50-foot frontage, a utility pole relocation or an upsized water main can turn a project that penciled into one that doesn't.

SB 1014 moves that conversation to the beginning. The preliminary application already exists under the Housing Crisis Act of 2019 (SB 330): it locks in the development standards and fees in effect when you file. Now that same filing can also ask "what will you make me build in the street?"

What the estimate leaves out

  • Improvements required by other agencies or utilities, such as a water district or the electric utility. For those, you can ask the agency yourself within 30 days of filing, and it must give you a list of the types of improvements within 30 business days.
  • Improvements imposed as CEQA mitigation.

The itemized list at building permit: the part with teeth

The second obligation is the stronger one. Once your building, grading or other postentitlement phase permit application is complete, the city has 30 business days to give you an itemized list of every onsite and offsite improvement it will require for that permit. After that, it can't add improvements that aren't on the list, except in three cases:

  1. The city finds, based on substantial evidence, that the improvement is needed to mitigate or avoid a specific, adverse impact on public health or safety.
  2. You change the scope of the work, and the new improvement is reasonably related to that change.
  3. The permit is a discretionary one and the improvement is CEQA mitigation.

This pairs with AB 1621's two-round plan check limit, signed the same day. Between the two bills, the building permit stage in 2027 gets a fixed number of correction rounds and a fixed list of required improvements. Keep the list and every correction letter; if a new requirement shows up in round two, the list is your answer.

How SB 1014 fits ADU, SB 9 and SB 684 projects

The bill uses the Permit Streamlining Act's definition of a housing development project and adds one thing expressly: parcel maps and tentative and final maps for SB 684 small-lot subdivisions. That's useful, because a 10-lot starter-home subdivision is exactly where frontage improvements, new laterals and fire access get expensive.

  • SB 684 / SB 1123 subdivisions: covered by name. Request the estimate with your preliminary application.
  • Multi-unit projects and density bonus projects: covered as housing development projects.
  • SB 9 lot splits and duplexes: likely covered for the housing development; whether the city treats the parcel map itself as covered is worth asking about in writing.
  • Single ADUs: state ADU law already limits what a city can require (no new utility connection or capacity charge for most ADUs converted within an existing home, and proportionate fees otherwise). Whether a standalone ADU permit triggers SB 1014's lists isn't spelled out. Not legal advice; a land-use attorney should confirm how it applies to your lot.

For cost planning, the improvements estimate is one more input next to impact fees. Our California ADU cost guide covers construction ranges, and the SB 1117 impact fee post covers what changes on fees in 2027.

Our recommendation

For any project you file in 2027, make the SB 1014 request standard practice. It arrives within 30 business days and tells you whether to buy, redesign or walk before you're deep into civil engineering. Ask every outside utility for its list in the same 30-day window. Then, when the postentitlement list arrives, compare it line by line with the early estimate and with your budget. Typical frontage and utility costs vary widely by city and site; get bids, and check your city's public works standards before you commit.

Frequently asked questions

What does SB 1014 require cities to do?

If you ask in your preliminary application or full application, the city must give you, within 30 business days, a good-faith list of the onsite and offsite improvements it may require and a cost estimate for any it would build itself. After a building or other postentitlement permit application is deemed complete, it must give an itemized list of required improvements within 30 business days.

Is the SB 1014 improvement estimate binding?

The early estimate is informational only and not legally binding. The itemized list at the postentitlement permit stage is different: the city generally can't require improvements that aren't on it, except for specific health-and-safety findings, scope changes you make, or CEQA mitigation on discretionary permits.

When does SB 1014 take effect?

January 1, 2027. It was signed September 29, 2026 as Chapter 806, Statutes of 2026.

Does SB 1014 apply to ADUs and SB 9 lot splits?

It applies to housing development projects as defined in Government Code section 65905.5, plus SB 684 parcel and tentative maps. Whether a single ADU permit counts is not spelled out; ask your city in writing and have a land-use attorney confirm for your project.

Official bill text

Sources

  • SB 1014
  • required improvements estimate California
  • offsite improvements cost
  • onsite and offsite improvements housing
  • Government Code 65941.3
  • preliminary application SB 330
  • sidewalk and utility upgrade requirements
  • SB 684 parcel map improvements

Stay ahead of the next ADU bill.

New California housing bills, what they mean for your lot, and news from Parcy and Kaz Capital Group. A few emails a month.

By subscribing you agree to receive email from Parcy and Kaz Capital Group — bill updates, guides, and other news from us. Unsubscribe anytime. Privacy.

Informational only. Not legal, architectural, or investment advice. Confirm current rules with your local planning department.