AB 1332: Pre-Approved ADU Plans and the 30-Day Permit Rule

Every California city now has to run a pre-approved ADU plan program. Use one of those plans for a detached ADU and the city has 30 days, not 60, to decide your permit.

By Kasra ErfanianPublished ← All guides

AB 1332: Pre-Approved ADU Plans and the 30-Day Permit Rule

Informational only, not legal advice. ADU rules change often and differ by city. Confirm with your local planning department before you rely on anything here.

AB 1332, by Assemblymember Juan Carrillo, is the law behind every city's catalog of pre-approved ADU plans in California. It passed the Senate 39-0 and the Assembly 75-0 in September 2023, was chaptered on October 11, 2023 (Chapter 759, Statutes of 2023), and gave every city and county until January 1, 2025 to run a pre-approval program. The part that matters most to a homeowner: if you build a detached ADU from a plan the city has already approved, the city has 30 days to approve or deny your permit instead of the usual 60.

What this means for your lot

If a detached ADU from your city's pre-approved list fits your backyard, you skip most of the design phase and the permit clock drops to 30 days from a complete application. The plan only covers the building itself. Your site plan, foundation, utilities and zoning check (setbacks, height, fire zone) still get reviewed for your lot, so pick a plan that already fits your setbacks before you pay the plan owner. Check your city's program page: catalogs, fees and what can be customized vary by city.

What AB 1332 requires cities to do

The law added Government Code section 65852.27, and HCD's March 2026 ADU Handbook still cites it there. Every "local agency" (every city and county, charter cities included) had to set up a program that does five things:

  1. Accepts plans from anyone. The city may not restrict who submits a plan for pre-approval. Architects, prefab companies and homeowners can all apply.
  2. Reviews them under state ADU law. A plan is approved or denied under the same standards as any ADU permit. The city may charge the same fee it would charge for an ADU of that size.
  3. Posts approved plans online with the applicant's contact information, and takes a plan down within 30 days if its owner asks. Posting is not an endorsement.
  4. May borrow plans that the city drew itself or that another California agency pre-approved.
  5. Decides fast. A detached ADU application using a pre-approved plan gets an approve-or-deny decision within 30 days of a complete application.

The 30-day permit rule for pre-approved ADU plans

Normally a city has 60 days from a complete application to approve or deny an ADU permit. AB 1332 halves that for a detached ADU when the application uses either:

  • a plan the city pre-approved within the current triennial building code cycle, or
  • a plan identical to one used in a detached ADU application the city already approved in the current cycle.

That second option gets less attention than it should. If your builder already got the exact same detached ADU approved in your city this code cycle, the repeat application is on the 30-day clock, with no catalog plan needed.

The catch is the code cycle. California rewrites its building code every three years, and the 2025 edition took effect January 1, 2026. A plan approved under the 2022 code no longer qualifies for the 30-day track until it is updated and approved again. Ask the plan owner which code edition the plan was approved under before you buy.

Custom detached ADUPre-approved or repeat plan
City decision deadline60 days from complete application30 days from complete application
Design workFull architectural set for your lotSite plan, foundation and utility sheets for your lot
Plan check on the buildingFull reviewAlready done; lot-specific items only
Who owns the designYou, through your architectThe plan owner, who licenses it to you

The 30-day clock starts at a complete application. Under SB 543 the city has 15 business days to say whether it is complete, so the realistic window from first submittal is longer. We walk through every step in our ADU permit process guide.

What a pre-approved plan does not cover

A pre-approved plan has already passed plan check for the building itself: structure, energy, plumbing and the rest of the building code. It has not been checked against your lot. Expect the city to review:

  • Fit on the lot: 4-foot side and rear setbacks, height limits, and distance from the house and other structures.
  • Foundation and soils: a hillside, expansive soil or a liquefaction zone can mean an engineered foundation the standard plan does not include.
  • Fire and utilities: fire-zone construction, sewer and electrical capacity.
  • Local overlays: coastal zone, historic districts and similar rules still apply. Check your city's ADU ordinance.

Customization is usually limited to finishes and colors. Move a wall and you are back to a custom plan on the 60-day track.

Are pre-approved ADU plans free?

Sometimes. Some cities and counties publish plans they paid for themselves. Most catalog plans are privately owned and licensed for a fee the plan owner sets. Either way you still pay the city's permit and plan check fees, and impact fees on a unit over 750 square feet. Our ADU cost guide shows where design fees fit in a total budget, as a typical range; your bids will differ.

How pre-approved plans fit Parcy's pathways

AB 1332's fast track covers detached ADUs, which is most of what we build:

  • Single-family lots: a pre-approved detached ADU plus a JADU in the house is the fastest version of the two-ADU rule. Starting January 1, 2027, AB 956 allows two detached ADUs, and a catalog plan built twice is the obvious way to use it.
  • Multifamily lots: under SB 1211 you can add up to eight detached ADUs. The statute's 30-day rule speaks to any detached ADU application, not only single-family lots, but site review on an apartment lot (fire access, utilities, open space) is heavier.
  • SB 9 and SB 684 lots: these are new homes, not ADUs, so AB 1332 does not apply to the homes themselves. An ADU added later can use it.

Our recommendation: start with the lot, not the catalog. Confirm buildable area, setbacks and utility runs first, then filter your city's list for plans that fit. If a city misses the 30-day deadline, write it down. A 2026 appellate ruling says cities can owe damages for ADU permit delays. This is not legal advice; a land-use attorney should confirm your options before you rely on it.

Frequently asked questions

What is AB 1332?

A 2023 California law (Chapter 759) that required every city and county to set up a program for pre-approved ADU plans by January 1, 2025, and to decide detached ADU permits that use those plans within 30 days of a complete application.

Are pre-approved ADU plans free?

Sometimes. A few cities and counties publish plans they own, but most catalog plans belong to private designers who charge a license fee. You still pay the city's permit, plan check and any impact fees.

How fast is an ADU permit with a pre-approved plan?

The city must approve or deny a detached ADU using a pre-approved plan, or a plan identical to one it already approved this code cycle, within 30 days of a complete application. The standard deadline is 60 days.

Can I change a pre-approved ADU plan?

Usually only cosmetic items such as finishes, colors and some windows and doors. Structural or layout changes turn it into a custom plan with full review. Check your city's program rules.

Official bill text

Sources

  • AB 1332
  • pre-approved ADU plans
  • pre-approved ADU plans California
  • ADU standard plan program
  • 30-day ADU permit
  • are pre-approved ADU plans free
  • detached ADU permit timeline

Stay ahead of the next ADU bill.

New California housing bills, what they mean for your lot, and news from Parcy and Kaz Capital Group. A few emails a month.

By subscribing you agree to receive email from Parcy and Kaz Capital Group — bill updates, guides, and other news from us. Unsubscribe anytime. Privacy.

Informational only. Not legal, architectural, or investment advice. Confirm current rules with your local planning department.